Custis Trail Marked up for Construction

Our Community Forums Road and Trail Conditions Custis Trail Marked up for Construction

Viewing 12 posts - 31 through 42 (of 42 total)
  • Author
    Posts
  • #927178
    Dirt
    Participant

    @CCrew 4725 wrote:

    Speaking of Dirt, where’s that rascal been?

    Sorry. I was in training part of last week and was up in the Philly suburbs scaring the crap out of the locals. I guess I took that whole “City of brotherly love” thing a bit too seriously.

    I missed y’all too. :D

    #927547
    Tim Kelley
    Participant

    Another update:

    “FYI: The contractor will begin overlaying the pavement on the Custis Trail very soon. They will begin at marker 12 close to Lee Highway, and work their way west. Please follow any detour signage that is in place. Updates to follow.”

    #927665
    Tim Kelley
    Participant

    “Paving on the Custis Trail is beginning today. The starting point has changed due to the logistics of the operation. Paving will start West of the original plan and begin at the Stafford Street ramp then progress Eastward.

    Today, Wednesday July 6, the Custis trail will be detoured onto 15th Street from the Quincy Street ramp to Vermont Street. Follow the detour signage. Other construction activity is occurring on 15th Street so use caution while on the road. The paving of this section is expected to be completed late today. Additional paving will resume next week between Quincy Street and Monroe Street.

    Updates will be sent as work progresses.”

    #927693
    Tim Kelley
    Participant

    “The contractor has informed me that they did not complete this section today and will complete the paving in the area tomorrow (July 7).”

    #927696
    CCrew
    Participant

    @Tim Kelley 5350 wrote:

    Today, Wednesday July 6, the Custis trail will be detoured onto 15th Street from the Quincy Street ramp to Vermont Street.

    Other construction activity is occurring on 15th Street so use caution while on the road.

    Government planning at it’s finest. Detour traffic due to construction onto a road that’s under construction. :)

    @Tim Kelley 5381 wrote:

    “The contractor has informed me that they did not complete this section today and will complete the paving in the area tomorrow (July 7).”

    Rumor has it they were delayed by killer pothole ducks…..

    #927719
    americancyclo
    Participant

    The newly paved section between Vermont and Quincy is really nice. Very smooth under the parking structure. Repave more!

    #927746
    Tim Kelley
    Participant

    “The contractor has moved beyond the projected section and will complete resurfacing up to the Lincoln Street ramp today. The detour takes you around to 14th Street, then back on the Custis trail. This section of the Custis Trail is expected to be open Friday 7/8.”

    #927789
    consularrider
    Participant

    Any one heading home tonight, please post the trail status since I have to ride that way for the first time in a couple of weeks at 5:30 tomorrow morning. :)

    #927891
    Dirt
    Participant

    The new pavement is super creamy. No lines on it yet, but it was smooth enough to lick. Don’t bother though. It didn’t taste very good. I tried it.
    5926078840_b6808e924b_b.jpg

    #927912
    americancyclo
    Participant

    paved all the way to Lincoln St now!

    #928138
    JeffC
    Participant

    Tim,
    I agree that the path is much better now since the paving. It was a bit unclear from the past posts, but is there any chance for additional repaving this year? In particular the stretch going from approximately where the current paving just ended (near the two artifical ponds at Lincon Street) eastward until the trail crosses Lee Hwy near Irving Street is also particularly bad with a number of “natural speedbumps” (aka tree roots pushing up the pavement). I believe this part should be paved next if possible.

    #928173
    Tim Kelley
    Participant

    @JeffC 5868 wrote:

    Tim,
    I agree that the path is much better now since the paving. It was a bit unclear from the past posts, but is there any chance for additional repaving this year? In particular the stretch going from approximately where the current paving just ended (near the two artifical ponds at Lincon Street) eastward until the trail crosses Lee Hwy near Irving Street is also particularly bad with a number of “natural speedbumps” (aka tree roots pushing up the pavement). I believe this part should be paved next if possible.

    From what I understand, the limiting factor of how much of the trail can be repaved is funding.

    I’d encourage you to send your comments to the Department of Parks, Recreation and Cultural Resources, (trails@arlingtonva.us) 703-228-6524.

Viewing 12 posts - 31 through 42 (of 42 total)
  • You must be logged in to reply to this topic.