    Arlington County will be rehabilitating the sanitary sewer pipe running along Four Mile Run Trail beginning the week of June 13 through the week of July 11 (dates may change due to unforeseen circumstances). The work will result in sections of Four Mile Run Trail being closed; the W&OD Trail will remain open and should be used instead for the duration of the project.

    Details can be found here.

  2. #2
    Join Date
    Dec 2010
    Location
    Winchester, VA
    Posts
    931
    Post Thanks / Like

    Default

    I always found "sanitary sewer" to be such an oxymoron


    Thanks for the heads up.

  3. #3
    Join Date
    Feb 2010
    Location
    Falls Church
    Posts
    4,298
    Post Thanks / Like

    Default

    Quote Originally Posted by CCrew View Post
    I always found "sanitary sewer" to be such an oxymoron


    Thanks for the heads up.
    I like that they're putting it into a rehab program instead of just replacing it. Sanitary sewers are valued members of the community that should not just be thrown away... especially when there's a program for getting them clean and sober.

    Pete

  4. #4
    Join Date
    Dec 2009
    Location
    Ballston - Rosslyn
    Posts
    3,162
    Post Thanks / Like

    Default

    Update on this:

    AM-Liners will resume the relining work on 27 inch sanitary sewer trunk line in Four Mile Run Trail area starting Monday 6/20/11.

    1 .Mon 6/20: Temporary bypass pumps & accessories will be installed next to the small parking lot leading in the dog exercise area of Glen Carlin Park. The parking lot, wooden bridge leading into the trail, including prtion of this trail will be closed. The parking lot next to the pavillion (impervious concrete area) and the upper lot on S. Harrison St. are available. The playground and dog exercise area will be accesible only from one side. The restroom facilities and parking area are open. Detour signs will be posted. WD&D trail traffic will not be impeded.

    2. Tues 6/21: Actual insertion of the liner and curing process begins.

    3. Wed 6/22: Curing process ends in the late afternoon. Breakdown of equipment begins.

    4. Thurs 6/23: Clean up and relocate pumps and piping to a safe place. Portion of the upper parking lot on S. Harrison St. may be used.

  5. #5
    Join Date
    Dec 2009
    Location
    Ballston - Rosslyn
    Posts
    3,162
    Post Thanks / Like

    Default Another update:

    "AM-Liners will resume the relining work on 27 inch sanitary sewer trunk line in Four Mile Run Trail area starting Monday 7/11/11. This week work area is from the dead-end of S. Arlington Mill Drive going toward Columbia Pike.

    1. Mon 7/11: Set up, clean and TV line.
    2. Tues 7/12: Liner will be inserted in the evening.
    3. Wed 7/13: Curing process begin. The FMR trail parallel to S. Arlington Mill Drive will be closed due to bypass pipes layout and insertion tower. Detour signs will be posted.
    4. Thurs 7/7: Breakdown of equipment, clean up. "

  6. #6
    Join Date
    Jul 2010
    Posts
    282
    Post Thanks / Like

    Default

    Watch out for the trucks

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •