Thread: Milling and Repaving Bluemont Connector Trail in Mid-August 2020

  1. #1
    Join Date
    Apr 2012
    Location
    Arlington
    Posts
    331
    Post Thanks / Like

    Default Milling and Repaving Bluemont Connector Trail in Mid-August 2020

    Forum members,

    Arlington Parks is proposing the following MOTs/Detours for work on the Bluemont Connector.

    Please sent comment BY JULY 3.

    [begin shared text from Arl DPR below)

    Wed like to share the draft maintenance of traffic (MOT) plan so that you are aware of the suggested detours that were anticipating to take place during the construction period, and share your feedback to help us ensure the MOT works well for cyclists and pedestrians.


    Right now, construction is planned to take five days during mid-August, 2020. As you can see by the attached maps, we have a different draft MOT for the three phases of construction that will take place. All construction will happen between the hours of 9 a.m. and 4 p.m. on each day, allowing bicyclists and pedestrians to use the trail as they normally would outside of those hours.


    We plan on communicating the finalized MOT plan and detours to the broader community starting at the end of July, but wanted to see if you or other members of the Bike and Walk Arlington have any feedback on the draft MOT as it stands today. Juan Du (jdu@arlingtonva.us), the project manager CCd in this email, would like to use any thoughts you provide to help inform the final draft.

    Bluemont Junction Trail Milling&Repaving MOT Plan Concept Schedule_20200626_Email.pdf

    [end of insert]

    Henry

  2. #2
    Join Date
    Sep 2015
    Location
    Riverdale, MD
    Posts
    577
    Post Thanks / Like

    Default

    Thanks for sharing Henry. Rough timing though since Ive noticed an uptick in use of the Bluemont Junction Trail since the closure of all the metro stations west of Ballston. Same kind of synergy we are having with 66 West construction work concurrent with limited shuttle service in lieu of metro. Surely Arlington and Fairfax are coordinating infrastructure master plan schedules?

  3. #3
    Join Date
    Mar 2015
    Location
    Falls Church, VA
    Posts
    1,090
    Post Thanks / Like

    Default

    Quote Originally Posted by SarahBee View Post
    Surely Arlington and Fairfax are coordinating infrastructure master plan schedules?
    lol

  4. Likes Judd, rcannon100, Henry, Sunyata, Steve O liked this post
  5. #4
    Join Date
    Feb 2011
    Location
    Crystal City to L'Enfant Plaza
    Posts
    2,314
    Post Thanks / Like

    Default

    Any chance we can get a bit of scope creep? The portion of the trail just north of Wilson where you emerge from under the roadway and then reconnect to the W&OD could use some help. Maybe 50-75 feet of asphalt.

  6. Likes SarahBee, bentbike33, Starduster liked this post
  7. #5
    Steve O's Avatar
    Steve O is offline 5000+ Posts? The first step to beating addiction is admitting you have one.
    Join Date
    May 2010
    Location
    Pentagon City in Arlington VA
    Posts
    5,189
    Post Thanks / Like

    Default

    Quote Originally Posted by dbb View Post
    Any chance we can get a bit of scope creep? The portion of the trail just north of Wilson where you emerge from under the roadway and then reconnect to the W&OD could use some help. Maybe 50-75 feet of asphalt.
    Where?

  8. #6
    Join Date
    Apr 2012
    Location
    Arlington
    Posts
    331
    Post Thanks / Like

    Default

    Quote Originally Posted by Steve O View Post
    Where?
    Whew! I thought it was just me.

    Dana, while I suspect the answer will be no on the scope creep (it has been every time I've asked), can you be more specific about where this is? The Bluemont Connector does not go under a roadway at any point.

    Henry

  9. #7
    Join Date
    Feb 2011
    Location
    Crystal City to L'Enfant Plaza
    Posts
    2,314
    Post Thanks / Like

    Default

    Click image for larger version. 

Name:	Doc1.jpg 
Views:	85 
Size:	88.8 KB 
ID:	21558

  10. #8
    Steve O's Avatar
    Steve O is offline 5000+ Posts? The first step to beating addiction is admitting you have one.
    Join Date
    May 2010
    Location
    Pentagon City in Arlington VA
    Posts
    5,189
    Post Thanks / Like

    Default

    Quote Originally Posted by dbb View Post
    Click image for larger version. 

Name:	Doc1.jpg 
Views:	85 
Size:	88.8 KB 
ID:	21558
    If we want to creep that far, I'd also love to have all the root heaves just south of Wilson fixed up, too.

  11. Likes Henry, Starduster liked this post
  12. #9
    dasgeh's Avatar
    dasgeh is offline Queen of Family Biking & All Things Kidical
    Join Date
    Aug 2011
    Posts
    5,788
    Post Thanks / Like

    Default

    That's not just scope creep, the W&OD Trail is not Arlington's. It belong to NOVA Parks. The good news is NOVA Parks has a nice budget for trail maintenance, so I'd shoot them a line about root heaves and other pavement issue on the trail.

  13. #10
    Join Date
    Feb 2011
    Location
    Crystal City to L'Enfant Plaza
    Posts
    2,314
    Post Thanks / Like

    Default

    An update from ArCo Parks and Rec

    "The schedule update is that the on-call contractor is not available until the week of October 12"